Setup Menus in Admin Panel

+447946739882, +2348151453146   INFO@CHESSSUBSEAENGINEERING.ORG
     

Home Forums Offshore Top Side & Subsea Engineering Open Forum Offshore Jackup Rigs Engineering Design & Analysis

Offshore Jackup Rigs Engineering Design & Analysis

Viewing 7 posts - 1 through 7 (of 7 total)
  • Author
    Posts
  • #4425

    Kelvin
    Keymaster

    Foundations

    Spud Can, Mat & Gravity foundations are used in jack up rigs design for the transfer of load to the sub soils.

    Note
    Spud Can foundations are used predominantly for most of the mobile drilling rigs.Other forms are used in special cases.

    #4426

    Lucas
    Participant

    Jacking Systems

    Offshore jacket legs can be lowered or raised using jacking system. Jacking system general consist of either Hydraulic or Electric device and a gear arrangement or Rack and Pinion arrangement on the legs.

    #4427

    Lucas
    Participant

    Geotechnical Aspects

    Geotechnical aspect needed to be investigated prior to mobilization and installation of jackup rigs at drill site are Hazard at site such as seabed conditions, environmental parameters etc, Evaluation of possible failure modes, Evaluation of ballast capacity to achieve the pre-load condition, Evaluation of bearing capacity for operating conditions, Effect of jackup leg penetration and its effect on the jacket piles in the vicinity, Effect of jackup leg withdrawal and loss of lateral support for the jacket piles in the vicinity and Evaluation of jacket stability during storm conditions.

    #4432

    Mohammed
    Participant

    Analysis of Jackups

    Typical jackup analysis involves the following stages:

    I. Identification of legs as simplified model as beam element with spring supports below soil and connected to the hull.
    II. The hull can be modeled using plate or equivalent beam element.
    III.Estimation of global environmental loads
    IV. Estimation of gravity & operational loads
    V. Global analysis using non-linear analysis to account for large displacements.

    #4433

    Mohammed
    Participant

    Leg Design

    Design of legs involve the following steps:

    I. Estimation of wave and current induced loads either by global analysis based on maximum base shear method or maximum moment method.
    II. Estimation of gravity loads and wind induced shear from the super structure.
    III.Design of lattice truss by simplified method or by the global analysis and design of each lattice members.

    #4434

    Mohammed
    Participant

    Indirect Design

    Energy absorption requires the structure to behave in a ductile manner. Mesures to obtain adequate ductility are

    I. Provide connections of primary members with strength exceeding that of the parent member.
    II. Provide redundancy in the structure such that alternate load distribution may be developed.
    III.Avoid dependence on energy adsoption in struts with a sharply decreasing post buckling capacity.
    IV. Select materials with sufficient fracture toughness properties.
    V. Select materials such that the ultimate tensile strenght is higher than the yield strenght to avoid rupture to occur at first yield eben if the
    fracture toughness is high.
    VI. Design joints and members to maintain their capacity through substantial concentrated inelastic deformation, to meet compact section
    requirement.

    #4542

    Kelvin
    Keymaster

    Sources of Fire

    I. Hydrocarbon Direct Fire (i.e. Fuel, Ignition and Oxygen).
    II. Blast Initiated Fire.
    III.Collission Initiated Fire.
    IV. Dropped Object Initiated Fire.
    V. Select materials such that the ultimate tensile strenght is higher than the yield strenght to avoid rupture.

Viewing 7 posts - 1 through 7 (of 7 total)
  • You must be logged in to reply to this topic.

Get Social with US ON FACEBOOK

9 inch Subsea Production Riser Steep Wave Configuration ORCAflex Simulation

8 inch Subsea Production Riser Lazy S Wave Configuration ORCAflex Fatigue Simulation

8 inch Subsea Production Riser Lazy S Wave Configuration ORCAflex Fatigue Simulation

Transient Flow Over a Cylinder : Pressure Contour

Live Testimonials from some of our Candidates

Transient Flow Over a Cylinder : StreamLine Velocity

Engineering of Subsea Production Systems Level 1 and Level 2

Transient Flow Over a Cylinder : Eddy Viscosity

Subsea Hydraulic Flying Leads & Cable Cutters Engineering Design

Steel Catenary Riser & Hook Up Components Engineering Design

SURFs Carousel Engineering Design 3D Animations

Piggyback Block Render & Subsea Bend Restrictor Engineering Design

16 inch Subsea Pipe Pull In Installation Simulation with ORCAFLEX

16 inch Subsea Lazy S Riser with Mid Water Arch Orcaflex Simulation

8 inch Subsea Production Pipeline S Lay Installation Simulation via Articulated Stinger

Subsea Riser Bouyancy Modules 3D Front End Engineering Conceptual Design & Simulations

10 inch Production Pipeline S Lay Installation Simulation via Articulated Stinger ORCAflex Explicit

16 inch Subsea Pipeline Davit Lift Orcaflex Simulation

8 inch Subsea Production Steel Catenary Riser ORCAflex Simulation

2 x 10 inch Subsea Production Riser Pliant Wave Configuration ORCAflex Simulation

ENGINEERING COMPETENCE AT ITS BEST!

From talent development and organizational performance to engineering and operational needs, we are driven by one goal: improve your performance through innovative solutions.

Continuing Professional Development

Our Renewable Energy, Offshore & Subsea Engineering CPD OJT courses are structured for engineers seeking to attain or maintain Chartered Status. Get to know more.

Computational Fluid Dynamics (CFD)

Using CFD, you are able to analyze complex aerodynamics and hydrodynamics problems involving fluid-fluid, fluid-solid or fluid-gas interaction.

top
© 2023. All Rights Reserved.
X